Job Information

Client

Loreto Sixth Form College

H & S

Site Managers

Value

£ 17,500.00

Duration

2 weeks

Before Pictures

During & Finished Pictures

Summary

CONCRETE HARDSTANDING AND DRAINAGE WORKS 

Preliminaries 

Travel 

Pre-start Meeting 

Provide RAMS for all work activities  

Cordon off work area top and bottom of site 

Mechanically cut down existing trees as required 

Mechanically excavate trench using 3 ton machine approx. 300(d) x 30600(l) x 3200/4500(w) 

Supply & lay 100mm of class 1 MOT compacted using 

Supply & Lay 200mm square edge concrete edgings to match existing to the rear of the proposed slab approx. 31Lm 

Supply & lay 1200s DPM 

Supply & Fix 1 layers of A393 reinforcing steel me  

Install shuttering for expansion joints 

Supply & Lay 35 gauged concrete approx. 180 x 4500 x 3200/4500mm approx. 120M2 (21.2M3) 

Allowance to made for 15mm expansion joints, Slab to laid in 3 sections 

Agitated with vibrating poker 

Float & Brush to a finish  

Drainage Works 

Excavate trench 2000 x 150 x 150mm 

Supply & Lay A15 100mm channel drain set in gauged concrete 

Make good any effected surfaces 

Project Particulars 

Scope of Works  

  • Pre start and preliminaries  
  • RAMS 
  • Site set up site
  • Operation of Heavy Plant 
  • Excavation 
  • Shuttering 
  • Reinforced Mesh 
  • Concreting 
  • Channel drains 
  •