Job Information
Client
Loreto Sixth Form College
H & S
Site Managers
Value
£ 17,500.00
Duration
2 weeks
Summary
CONCRETE HARDSTANDING AND DRAINAGE WORKS
Preliminaries
Travel
Pre-start Meeting
Provide RAMS for all work activities
Cordon off work area top and bottom of site
Mechanically cut down existing trees as required
Mechanically excavate trench using 3 ton machine approx. 300(d) x 30600(l) x 3200/4500(w)
Supply & lay 100mm of class 1 MOT compacted using
Supply & Lay 200mm square edge concrete edgings to match existing to the rear of the proposed slab approx. 31Lm
Supply & lay 1200s DPM
Supply & Fix 1 layers of A393 reinforcing steel me
Install shuttering for expansion joints
Supply & Lay 35 gauged concrete approx. 180 x 4500 x 3200/4500mm approx. 120M2 (21.2M3)
Allowance to made for 15mm expansion joints, Slab to laid in 3 sections
Agitated with vibrating poker
Float & Brush to a finish
Drainage Works
Excavate trench 2000 x 150 x 150mm
Supply & Lay A15 100mm channel drain set in gauged concrete
Make good any effected surfaces
Project Particulars
Scope of Works
- Pre start and preliminaries
- RAMS
- Site set up site
- Operation of Heavy Plant
- Excavation
- Shuttering
- Reinforced Mesh
- Concreting
- Channel drains